3. Bid solicitation preparation—Assessor Guidance Document—Supply Arrangement Requirements

Document navigation for "3. Bid solicitation preparation—Assessor Guidance Document—Supply Arrangement Requirements"

3.01 Bid solicitation—documentation

Copy of the bid solicitation document must be on file.

Assessment guidance and notes

A complete copy of the bid solicitation document, including but not limited to the Statement of Work (SOW), category/categories and levels required, security requirement, mandatory and point rated criteria, basis of selection, certifications, Flexible Grid (if applicable), resultant contract clauses etc. must be on file. Without a copy of the complete bid solicitation document, it is not possible for the Assessor to confirm the information sent to the Supplier.

Competitive Requirements

For requirements that have been re-tendered due to changes in the category/categories, level, security, etc. the Assessor will assess only the latest bid solicitation document and not the bid solicitation documents from earlier round(s) of bidding. However, if multiple rounds of bidding were required due to lack of responses or bid solicitation responses that were deemed to be non-compliant, the Contracting Authority should place a copy of the bid solicitation document from all preceding rounds of bidding on the contract file.

Procurements based on the "does not exceed $40k" rule

The Contracting Authority must ensure that there is documentation on file that confirms that the Supplier has been provided all necessary information, including but not limited to the SOW, category/categories required, levels required, mandatory criteria, certifications (if applicable), Flexible Grid (if applicable), resultant contract clauses etc. Contracting Authorities should issue a formal bid solicitation document and place a copy on file. If an informal process is used, all required documentation related to the bid solicitation process must be on file.

3.01 Bid solicitation - documentation Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) Copy of bid solicitation documentation is not on file and the Contracting Authority is unable to provide it.

Without a copy of all bid solicitation documents it is not possible for the Assessor to confirm compliance with a number of subsequent elements. (Contravention of TB Contracting Policy sub-section 12.3.1.)

Minor non-conformance Copy of bid solicitation documentation is not dated.

Failure to comply with the requirement does not meet the criteria applicable to a Major non-conformance.

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.02 Bid solicitation—parameters (search results)

Bid solicitation documents must be consistent with the search criteria used.

Assessment guidance and notes

The Assessor must verify that the category/categories, level of expertise, Supplier Security Clearance, Supplier Document Safeguarding and Region/Metropolitan Area stated in the bid solicitation document matches criteria used to conduct the search.

The following applies to Directed Requirements only:

  • If the supplier security clearance or document safeguarding level stated in the supplier's Centralized Professional Services System (CPSS) ePortal profile are higher than that stated in the bid solicitation, a non-conformance shall not be raised. The rationale being that the supplier selected would have been returned in the search results in either case
  • If the supplier security clearance or document safeguarding level stated in the supplier's CPSS ePortal profile is lower than that stated in the bid solicitation, a non-conformance will be raised if there is no documentation on file that confirms what the supplier security clearance or document safeguarding level was at the time the bid solicitation was issued

Note

  1. Category descriptions in Task Based Informatics Professional Services (TBIPS) Methods of Supply (MoS) contain reference to "Level 1", "Level 2" and "Level 3". These levels are equivalent to Junior, Intermediate and Senior levels referred to in CPSS search results for all other MoSs
  2. The longer the period of time between the date the search was conducted and the date of the bid solicitation, the higher the risk that one or more suppliers displayed in the original search results do not have an active Supply Arrangement (SA). For example, the search was conducted on January 2, 2018 and the bid solicitation was issued February 15, 2018. The SA for one of the suppliers, who was part of the original search results, was de-activated for failing to meet the terms of their SA on January 31, 2018. If the search was re-done on the date the solicitation was issued, this supplier would not have been returned
3.02 Bid solicitation - parameters (search results) Potential findings
Type Description Rationale
Major non-conformance—policy (other) The total estimated value, category/categories, level, Supplier Security Clearance, Supplier Document Safeguarding or Region/Metropolitan Area stated in the bid solicitation document is not consistent with search criteria used. Use of search criteria that is not consistent with the information stated in the bid solicitation will have a direct impact on the search results returned. If the correct criteria had been used, the list of Suppliers returned would be different. (Contravention of TB Contracting Policy sub-section 16.10.3).
Major non-conformance—procedural There is a significant discrepancy between the date the search was conducted and the date of the bid solicitation. The search results on file were conducted after release of the bid solicitation.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of all bid solicitation documents are not on file. If all bid solicitation documents are not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of either the initial or the final search results is not on file. If either the initial or final search results are not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 2.01: Search Results—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.03 Response period

Bid solicitation documents are to provide a minimum of 5 calendar days (requirements valued at $0 to NAFTA or the Canada Korea Free Trade Agreement (CKFTA) (after July 1st, 2020) or 15 calendar days (requirements valued at NAFTA or CKFTA to $3,750,000.00). For Temporary Help Services (THS) SA, lowest price selection are to provide a minimum of 48 hours, right fit a minimum of 96 hours and for competitive method 2, it is the identified user’s choice.

Assessment guidance and notes

Bid solicitations must provide Suppliers with a minimum period within which to respond. The minimum bid response times were developed, in consultation with suppliers and department users, to allow suppliers sufficient time to locate resources capable of completing the work. Contracting Authorities who provide a response time that is less than the requisite minimum must have written justification on file. Justification would be established through consultations with the client and possibly the identified suppliers.

When calculating the response period, the date shown on the bid solicitation document or the date the bid solicitation document was sent to the Suppliers (if different than the date shown on the bid solicitation document) is not counted. Where there are discrepancies with the date on both documents (e.g. date on bid solicitation document is January 7, 2020 and date of email is January 8, 2020), the date the bid solicitation document was sent to the Suppliers shall be used to determine compliance to this requirement. Where the bid solicitation document does not state the response date, the date that Suppliers are sent the bid solicitation document shall be assumed to represent the bid solicitation date and shall be used to determine compliance to this requirement.

Note

  1. For requirements under $40k where the exception "does not exceed $40k" has been invoked, there is no minimum bidding period.
  2. The above requirements also apply in the event that a requirement is re-tendered.
3.03 Response period Potential findings
Type Description Rationale
Major non-conformance—procedural Bid solicitation document provides a response time that is less than the requisite minimum amount. There is no justification on file. Without providing sufficient time for Suppliers to provide a response, potential Suppliers may not be able to submit a response.
Major non-conformance—procedural Bid solicitation document fails to specify the response due date. Without a response due date, potential Suppliers could submit a response at any time or submit amendments to their response at any point up until the point of contract issuance.
Observation (insufficient information) Bid solicitation document specifies response time that is less than the minimum required. The documented justification appears to be insufficient. The assessor does not have the necessary subject matter expertise or information to assign a non-conformance.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document and/or copy of documentation that confirms who was sent the bid solicitation are not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation). If documentation that confirms who was sent the bid solicitation is not on file, then a Major non-conformance would be raised against the next element (i.e. 3.17: Supplier’s List).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.04 Bid solicitation—content (part A—requirement details, competitive)

Bid solicitation documents must contain specific information.

Assessment guidance and notes

Bid solicitation documents must contain, as a minimum but not limited to, the following information:

  • Standard Instructions:
    • Bid submission instructions (address for submission of bids, bid closing date and time);
  • Bid preparation instructions
  • Bid evaluation procedures
  • Basis of selection
  • Financial capability (if applicable)
  • Certifications
  • Security Clause (if applicable)
  • Complete Security Requirement Check List (SRCL), except for part D—refer note below
  • Resulting contract clauses (including Task Authorization (TA) clauses, travel, etc. if applicable)
  • Complete description of the work (i.e. SOW)

Bid solicitation documents for all MoSs, with the exception of ProServices and Temporary Help Services (THS), must use the "High Complexity Bid Solicitation and Resulting Contract Template (HC)" bid solicitation template available in the Standard Acquisition Clauses and Conditions (SACC) Manual. Bid solicitation documents issued using the ProServices MoS must use the "Medium Complexity Bid Solicitation and Resulting Contract Template (MC)" bid solicitation template available in the SACC Manual. THS must use one of the three (3) templates available on the THS Web site. The HC and MC and THS bid solicitation templates contain clauses that must appear in the bid solicitation document and clauses that are only required in specific circumstances. When determining compliance to this element, Assessors must determine whether or not all required information as identified above including all appropriate clauses have been incorporated into the bid solicitation document.

Note

  1. Security Requirements—The bid solicitation document may or may not require that the Supplier or the resource(s) offered or both have a specific level of security clearance
  2. SRCL—Part D, Authorization, provides information that the Contracting Authority may not want to publish during the solicitation period (e.g. name, phone number and email address of the Contract Security Program (CSP) Security Officer, the Departmental Security Officer (DSO), etc.
  3. Complete description of the work—May also be referred to as the Statement of Work, Statement of Requirements, etc.
  4. Bid Preparation Instructions—Requirements for the Technical Bid, including (if applicable) submission of resumes, academic certification(s); Financial Bid; Certifications (if applicable) and other information (if applicable)
  5. Bid Evaluation Procedures—This includes evaluation process including evaluation team composition and identification of mandatory technical criteria (if applicable) and point rated evaluation criteria (if applicable)
  6. Basis of Selection—Selection type (e.g. bid with the lowest evaluated price, lowest evaluated price per point, etc.)
  7. Basis of Payment - Annex B, Basis of Payment, of the "High Complexity Bid Solicitation and Resulting Contract Template (HC)" for the TBIPS and TSPS MoS does not include a column for level of effort. Therefore, a non-conformance shall not be raised if the Annex B, Basis of Payment does not include a level of effort
3.04 Bid solicitation - content (part A - requirement details, competitive) Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) Bid solicitation document fails to include all required components (clauses, parts, annexes, etc.). TB Contracting Policy requires that bid solicitation documents contain all required components (clauses, parts, annexes, etc.) that ensure that the contracting process will stand up to public scrutiny and meet Canada's obligations under the various free trade agreements. (Contravention of TB Contracting Policy sub-sections 2, 4.1.2, 4.1.4, 4.2.11, 4.2.12, 4.2.23, 5.2.1, 8.4.1, 9.1.2, 10.3.1.)
Major non-conformance—policy (other) There are major discrepancies or inconsistencies within the bid solicitation document. The contradictory information presented makes it impossible for Suppliers to present a compliant resource and could affect the selection process and consequently change the Supplier awarded the contract. (Contravention of TB Contracting Policy sub-section 10.7.27)
Major non-conformance—procedure SRCL attached to the bid solicitation, refer Part D, was not signed as approved by the CSP and/or the Organization Project Authority or Organization Security Authority. TB Policy on Government Security requires that SRCL attached to the bid solicitation is approved before the solicitation document is issued. (Contravention of TB Policy on Gov't Security sub-section 5.9 and Appendix A.6).
Major non-conformance—procedure There are significant discrepancies between the bid solicitation instructions and the instructions related to the selected MoS. There are specific rules associated with each MoS under the CPSS ePortal. Results in the improper use of the them has a serious impact on the integrity of the procurement.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.05 Bid solicitation—content (part A—requirement details, non-competitive)

Bid solicitation documents must contain specific information.

Assessment guidance and notes

Bid solicitation documents must contain, as a minimum but not limited to, the following information:

  • Certifications (if applicable)
  • Security Clause (if applicable)
  • Completed SRCL (if applicable)
  • Resulting contract clauses
  • Complete description of the work (i.e. SOW)

Note

  1. Security Requirements—The bid solicitation document may or may not require that the Supplier or the resource(s) offered or both have a specific level of security clearance
  2. Complete description of the work—May also be referred to as the Statement of Work, Statement of Requirements, etc.
3.05 Bid solicitation - content (part A - requirement details, non-competitive) Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) Bid solicitation document fails to include all required components (clauses, parts, annexes, etc.). TB Contracting Policy requires that bid solicitation documents contain all required components (clauses, parts, annexes, etc.) that ensure that the contracting process will stand up to public scrutiny and meet Canada's obligations under the various free trade agreements. (Contravention of TB Contracting Policy sub-sections 2, 4.1.2, 4.1.4, 4.2.11, 4.2.12, 4.2.23, 5.2.1, 8.4.1, 9.1.2, 10.3.1.)
Major non-conformance—procedure SRCL attached to the bid solicitation, refer Part D, was not signed as approved by the CSP and/or the Organization Project Authority or Organization Security Authority. TB Policy on Government Security requires that SRCL attached to the bid solicitation is approved before the solicitation document is issued. (Contravention of TB Policy on Gov't Security sub-section 5.9 and Appendix A.6).
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.06 Bid solicitation—content (part B—requirement details, flexible grid)

Bid solicitation documents must contain the Flexible Grid (if applicable)

Assessment guidance and notes

The Flexible Grid applies to requirements that use either the TSPS Task Supply Arrangement or requirements for categories under Streams 8 to 12 (Non-IT Professional Services) of the ProServices MoSs only. The Flexible Grid indicates the minimum level of points required by each proposed resource to qualify for each Level of Expertise (i.e. Junior, Intermediate or Senior). Various amounts of points are given for relevant education, professional certification and relevant experience. The bid solicitation document must contain the following related to use of the Flexible Grid:

  • Statement indicating that the Bidder must demonstrate that each proposed resource offered meets the minimum number of points required for the relevant level and category described in the Flexible Grid(s)
  • A copy of the relevant Flexible Grid(s) or a reference to the Annex "A" Requirement of the TSPS Task Supply Arrangement

Note

  1. The Flexible Grid provides the general requirements that a resource must meet based on specific categories and levels
  2. The Flexible Grid does not apply to solution-based MoSs
3.06 Bid solicitation - content (part B - requirement details, flexible grid) Potential findings
Type Description Rationale
Major non-conformance—policy (other) There are significant discrepancies between the Flexible Grid contained in the bid solicitation document and the Flexible Grid applicable to the category required. The discrepancies suggest that there has been an attempt to manipulate the procurement process. (Contravention of TB Contracting Policy sub-section 10.7.25).
Major non-conformance—procedural Bid solicitation document fails to include the required information related to the Flexible Grid. Failure to provide the required items would prevent a Supplier from presenting compliant resource(s) and would prevent a third party from assessing the validity of any subsequent technical evaluation.
Major non-conformance—procedural Bid solicitation document includes a Flexible Grid for a solutions based MoS. The Flexible Grid is used to confirm the level of the resource being offered against a specific category. Solution-based MoSs do not include categories.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.07 Mandatory technical evaluation criteria—part A

Mandatory technical evaluation criteria must be consistent with the work described in the SOW and the Flexible Grid (if applicable).

Assessment guidance and notes

Mandatory evaluation criteria identify the minimum requirements that are essential to the successful completion of the work. Significant discrepancies between the mandatory criteria, the SOW and the Flexible Grid (if applicable) suggest that:

  • The work described in the SOW is inaccurate, or
  • The Flexible grid (if applicable), specifically the category (ies) or stream(s) and level (if applicable) selected are inaccurate, or
  • There is the appearance of an attempt to manipulate the procurement process

Discrepancies between the SOW, specifically the level of each category, and the mandatory requirements would invalidate the search conducted. In such a case, there is a high probability that, if the level of the category (ies) used matched the mandatory requirements, the search results would have been materially different. For example, the bid solicitation document required an Intermediate level (or level 2) Application/Software Architect. The experience required in the bid solicitation document was a minimum of fifteen (15) years. However, the experience requirement for this category at the specified level is 5 to less than 10 years' experience. Requiring a minimum of fifteen (15) years would be consistent with the specified category at the Senior level (or level 3).

Flexible Grid

If the Flexible Grid is applicable, mandatory criterion specified in the bid solicitation document must be consistent with the minimum requirements stated in the Flexible Grid for the category and level of expertise required. In addition, the total number of points, based on the mandatory requirements for education, certification (if applicable) and experience must be consistent with the level of expertise required. Please note the following examples:

  • Bid solicitation document requires a Business Analyst with an Intermediate level of expertise. The bid solicitation document states that the minimum education required is a High School Diploma. However, the minimum education requirements in the Flexible Grid applicable to the required category is either a University degree (PhD, Graduate, or Undergraduate) or College or CEGEP Diploma/Certificate. In this case the minimum education requirement is not consistent
  • Bid solicitation document requires a Human Resources Consultant with a junior level of expertise. The bid solicitation document includes the following mandatory criteria - University degree (undergraduate level), certification as a Certified Human Resources (HR) Professional (CHRP)) and minimum 10 years' experience. Resources offered that meet the mandatory criteria would achieve a score of 110 points (35 points for education, 15 points for the certification and 60 points for experience) when compared to the appropriate Flexible Grid. The total number of points in this case is consistent with a consultant at the Senior and not Junior level

Temporary Help Services

If the competitive method 1 is used, a maximum of 2 additional mandatory criteria is allowed. No rated or asset criteria allowed. If competitive method 2 is used, then additional mandatory and rated criteria are allowed.

Note

  1. The Contracting Authority may, at their discretion include in the bid solicitation document only the mandatory requirements required by the appropriate Flexible Grid
  2. For categories where a minimum level of education is stipulated, evidence of completion of a higher level of education will be accepted
  3. Contracting Authorities may, if applicable, specify a level of education that is higher than the minimum mandatory requirements provided that the level of education required does not exceed the education requirements identified as being mandatory for the next highest level. For example, the category Strategic Learning Advisor, at the junior level, requires either an undergraduate degree or college degree in any field. The same category, at the Intermediate level, requires:
    1. An undergraduate degree or college degree in any field, or
    2. An undergraduate degree with a Major in Education, Adult Learning, Distance Learning, or eLearning, or
    3. A graduate degree with a Major in Education, Adult Learning, Distance Learning, or eLearning

    If the Contracting Authority requires a Strategic Learning Advisor, with an undergraduate degree with a Major in Education, the Contracting Authority must request a resource at the intermediate level and not the junior level.

  4. The minimum requirement for each mandatory experience criterion must be consistent with the minimum experience requirement for the level of each category selected. If a category and level requires a minimum five (5) years of relevant experience and the next higher level requires a minimum ten (10) years, each mandatory experience criterion cannot be less than the minimum five years (e.g. two years) or exceed the minimum for the next higher level (e.g. 12 years)
  5. The requirements stated in this element apply to competitive bid solicitations and procurements based on the "does not exceed $40k" rule
3.07 Mandatory technical evaluation criteria - part A Potential findings
Type Description Rationale
Major non-conformance—policy (other) There are significant discrepancies between the mandatory criteria and the SOW, the search criteria used or the Flexible Grid (if applicable). Either the search criteria used was incorrect, thus invalidating the search conducted, or there is an attempt to manipulate the procurement process. (Contravention of TB Contracting Policy sub-section 10.7.25)
Major non-conformance—policy (other) There is more than 2 additional mandatory criteria for THS requirement, competitive method 1. THS Competitive method 1 does not allow more than 2 additional mandatory criteria (Temporary help services at a glance)
Observation (insufficient info) The mandatory technical evaluation criteria do not appear to be consistent with the SOW, the search criteria used or the Flexible Grid (if applicable). The assessor does not have the necessary subject matter expertise or information to assign a non-conformance.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the SOW is not on file. If the SOW was not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.03: Bid Solicitation—Content (Part A—Requirement Details, Competitive) or 3.04: Bid Solicitation—Content (Part A—Requirement Details, Non-Competitive)).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (other) The mandatory technical evaluation criteria were included in the SOW. Mandatory criteria or requirements that could be interpreted as mandatory criteria should not be included in the SOW. The intent of the SOW is to describe the work that is required. Inclusion of mandatory criteria in the SOW could result in contradictions between the SOW and the mandatory criteria stated elsewhere in the solicitation document, failure to evaluate the additional mandatory criteria, etc.

3.08 Mandatory technical evaluation criteria—part B

Mandatory technical evaluation criteria must be described with sufficient clarity so as to permit evaluator(s) to determine compliance on a pass/fail basis.

Assessment guidance and notes

Compliance of each mandatory technical requirement must be based on a simple "yes" or "no" answer. If judgement is required by the evaluator(s) to determine compliance then the bid solicitation document should provide guidelines so that Suppliers will know how their response will be evaluated. For example, the bid solicitation document requires a secondary school diploma. This requirement is clear, either the person has it or they do not. An example of a criterion that would require judgement is the requirement for a secondary school diploma or an acceptable combination of education, training and experience. In such cases, the acceptable combination education, training and experience must be specified.

Bid solicitation documents that fail to specify the minimum requirement for experience, knowledge required, minimum number of projects, minimum project duration, etc. will force evaluators to deem a resource compliant if, for example, that resource has one day of experience in a required area. Statements such as "experience in" and "significant experience in" do not identify a specific minimum amount of experience and as such, allow for discretionary evaluation.

Bid solicitation documents that fail to specify the recentness of the experience or project will force evaluators to deem a resource compliant if, for example, the experience was gained or the project was completed five, ten or twenty years ago.

The Contracting Authority must, for each mandatory technical requirement state how compliance will be determined. For criterion related to projects and experience, compliance can be determined via the resume submitted. However, compliance to criterion such as security clearance, professional designation, education, etc. should be substantiated through submission of objective evidence such as certificates, copy of diploma, etc. In the absence of a clear statement as to how compliance will be determined, the Contracting Authority will be forced to accept a simple statement from the Supplier as proof. In such situations an Observation shall be cited including a note in the comments stating that the assertion made by the Supplier would have to be accepted.

Note

The requirements stated in this element apply to competitive bid solicitations and procurements based on the "does not exceed $40k" rule.

3.08 Mandatory technical evaluation criteria - part B Potential findings
Type Description Rationale
Major non-conformance—policy (other) Mandatory technical evaluation criteria used lacks sufficient information to permit an evaluator to determine compliance on a pass/fail basis. Evaluation criteria used must allow evaluators to determine compliance based on a yes or no answer. TB Contracting Policy requires that evaluation factors be clearly defined so that they may be applied equally. (Contravention of TB Contracting Policy sub-section 10.7.27.)
Major non-conformance—policy (other) Mandatory technical evaluation criterion does state how compliance would be verified. Refer rationale above.
Major non-conformance—procedural Mandatory technical evaluation criteria used lacks specificity (e.g. fails to state minimum amount of experience required, minimum project duration, how recent the experience or project must be, etc.). Evaluation criteria used must be of sufficient clarity so that different evaluators can come to the same conclusion.
Major non-conformance—procedural Mandatory technical evaluation criteria used is too specific (e.g. requires an exact amount of experience required). Evaluation criteria used must be of sufficient clarity so that evaluators are able to make decisions based on the intent of the criterion.
Major non-conformance—procedural Mandatory technical evaluation criterion requires minimum amount of experience for several components but does not indicate whether the experience required is cumulative or must be demonstrated for each component. Evaluation criterion states that, for example, minimum 10 years of experience is required in web site design, web site content management and applying metadata standards to web content.

Based on the lack of clarity contained in this example, one evaluator could declare a resource non-compliant for failing to meet the minimum experience in all three components. Just as likely, the same evaluator could add up the experience in all three components and deem the resource compliant for this criterion because the cumulative experience exceeds 10 years. Finally, it is possible that the Contracting Authority, based on the example above, may be forced to accept a resource that does not have the minimum experience in all components specified.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation is not on file. If the bid solicitation document was not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation Preparation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (insufficient info) The mandatory technical requirements appear to lack sufficient information to permit an evaluator to determine compliance on a pass/fail basis. The Assessor does not have the necessary subject matter expertise or information to assign a Major or Minor non-conformance.

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.09 Mandatory technical evaluation criteria—part C

Mandatory technical evaluation criteria must not unfairly restrict competition.

Assessment guidance and notes

Mandatory technical evaluation criteria must not be construed as unduly restricting the ability of a Supplier to respond to the bid solicitation. Examples of such a situation includes, but is not limited to:

  • Requiring a minimum amount of experience within a very short time period (e.g. three (3) years within the last four (4) years)) given the category, level, description of the work required in the SOW, etc.
  • An unreasonable number of mandatory requirements given the category, level, description of the work required in the SOW, etc.
  • Experience required is unreasonable given the category, level, description of the work required in the SOW (e.g. requirement is for category 1.1 - Human Resources Consultant, level of expertise - junior. Minimum amount of relevant experience required is 10 years)
  • Certificate(s) required is unreasonable given the category, level, description of the work required in the SOW (e.g. requirement is for category 2.15 Facilitator Consultant, level of expertise - junior. Certificate required Master Facilitator Certification)

    Note: Master Facilitator Certification is a higher certification level than Certified Professional Facilitator.

  • Specific government related experience where the work must have been performed in a particular area within the federal government (e.g. requirement is for category 3.2 Project Manager, level of expertise—intermediate with a minimum ten (10) years' experience within a specific project office in National Defence)

Note

  1. In some cases, specific experience using software or a system or other tool that is found only in the federal government may be acceptable. Example would be minimum three (3) years' experience using the Financial Information System (FIS) in the federal government. Also, in some situations (e.g. IT Security Design Specialist), the skill sets required by a resource may be constantly evolving thus necessitating that the resource's experience be more recent than may otherwise be required for other categories
  2. The requirements stated in this element apply to competitive bid solicitations only
3.9 Mandatory technical evaluation criteria - part C Potential findings
Type Description Rationale
Major non-conformance—policy (other) Mandatory technical evaluation criteria fits one or more of the situations described in the Assessment Guidance and Notes section of this element and is considered to unfairly restrict the ability of a Supplier to respond to the bid solicitation. Evaluation criteria used must not be construed as providing a single Supplier with an unfair advantage or unduly restricting the ability of a Supplier to respond to the bid solicitation. (Contravention of TB Contracting Policy sub-section 9.1.1)
Observation (insufficient info) The mandatory technical evaluation criteria appear to unduly restrict the ability of a Supplier to respond to the bid solicitation. The assessor does not have the necessary subject matter expertise or information to assign a non-conformance.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the SOW is not on file. If the SOW was not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.03: Bid Solicitation—Content (Part A—Requirement Details, Competitive) or 3.04: Bid Solicitation—Content (Part A—Requirement Details, Non-Competitive)).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.10 Point rated technical evaluation criteria—part A

Point rated technical evaluation criteria must be consistent with the work described in the SOW and the search criteria used.

Assessment guidance and notes

Point rated technical evaluation criteria are used to assist in determining which bid solicitation response represents the best value. Significant discrepancies between the point rated criteria, the SOW or the search criteria suggest that:

  • The work described in the SOW is inaccurate, or
  • The search criteria, specifically the category (ies) or stream(s) and level (if applicable) selected are inaccurate, or
  • There is the appearance of an attempt to manipulate the procurement process
3.10 Point rated technical evaluation criteria - part A Potential findings
Type Description Rationale
Major non-conformance—policy (other) There are significant discrepancies between the point rated criteria and either the SOW or the search criteria used. Either the search criteria used was incorrect, thus invalidating the search conducted, or there has been an attempt to manipulate the procurement process. (Contravention of TB Contracting Policy sub-section 10.7.25)
Major non-conformance—policy (other) There is point rated criteria for THS requirement, competitive method 1. THS Competitive method 1 does not allow point rated criteria (Temporary help services at a glance)
Observation (other) The point rated criteria do not appear to be consistent with the SOW or the search criteria. The Assessor does not have the necessary subject matter expertise or information to assign a Major or Minor non-conformance.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the SOW is not on file. If the SOW was not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.03: Bid Solicitation—Content (Part A—Requirement Details, Competitive) or 3.04: Bid Solicitation—Content (Part A—Requirement Details, Non-Competitive)).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.11 Point rated technical evaluation criteria—part B

Point rated technical evaluation criteria must clearly describe the requirement.

Assessment guidance and notes

Criterion against which points are assigned must be clearly defined so that Suppliers have the information necessary to offer the best potential resource(s) and so that the Contracting Authority or Client can evaluate the resources offered and make decisions based on clearly described criteria.

The bid solicitation document must clearly describe the point rated criteria to allow those responsible for the technical evaluation to make appropriate and supportable scoring decisions. For example, if points are assigned to a post-secondary degree, the criterion must state the points assigned for each type of degree (i.e. undergraduate, graduate or doctoral), if applicable, and indicate the discipline or disciplines that would qualify for the assignment of points. Failure to do so could, for example, force an evaluator to accept degrees that have little or no relationship to the work required.

Bid solicitation documents that fail to specify the minimum requirement for experience, minimum project duration, etc. will force evaluators to assign points against projects where the resource has, for example, one day of experience in a required area. In addition, bid solicitation documents that fail to specify the recentness of the experience or project will force evaluators to assign points against projects that were, for example, completed five, ten or twenty years ago.

3.11 Point rated technical evaluation criteria - part B Potential findings
Type Description Rationale
Major non-conformance—policy (other) Point rated technical evaluation criteria are not clearly described and would result in inconsistent application. Evaluation criteria used must be of sufficient clarity so that different evaluators can come to the same conclusion and so that in the event that the evaluation is challenged, the criteria used can stand up to scrutiny. (Contravention of TB Contracting Policy sub-section 10.7.27)
Major non-conformance—procedural Point rated technical evaluation criteria used lacks specificity (e.g. fails to state minimum amount of experience required, minimum project duration, how recent the experience or project must be, etc.). Evaluation criteria used must be of sufficient clarity so that different evaluators can come to the same conclusion.
Observation (other) Point rated technical evaluation criteria states that the proposed resource(s) must meet minimum criteria specifically set out in the bid solicitation document. The use of the word "must" together with stating a minimum requirement implies that the requirement is mandatory. If there is a minimum requirement, the criterion should be included as part of the mandatory requirements.

Finding does not meet the criteria applicable to a Major or Minor non-conformance.

Observation (documentation) Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.12 Point rated technical evaluation criteria—part C

Point rated technical evaluation criteria must clearly indicate how each score will be determined.

Assessment guidance and notes

Scoring guidelines used for each point rated criterion must, when specific conditions occur, be able to return only a single value. Scoring guidelines that assign points based on multiple items such as projects must clearly indicate the number of points that will be assigned to each item or project.

For example, minimum requirement is for two (2) years of experience (specified as a mandatory requirement). Scoring guide assigns ten (10) points for greater than two (2) years' experience but less than five (5) years' experience and twenty (20) points for five (5) or more years of experience. Suppliers know that if they offer a resource with five (5) years' experience they will be assigned twenty (20) points for that criterion. However, using the same example above, the scoring guide assigns ten (10) points for two (2) to five (5) years' experience and twenty (20) points for five (5) or more years of experience. How will the evaluator determine the number of points to assign a resource with exactly five (5) years' experience?

Use of Rating Schemes:

In some cases, the bid solicitation document may include a table that provides additional information regarding how points are assigned to a project. For example, the point rated requirement may assign points based on a description of the approach that a bidder would take to complete the required work. In such cases, points would be assigned based on degree of understanding, clarity, completeness, etc. of the bidder. How points will be assigned must be clear. For example, if points are assigned based on the bidder's understanding of the requirement, there can be no ambiguity in the description of the various levels of understanding. In addition, there can only be one score assigned for each level. For example, if a point rated criterion assigns points based on the supplier's level of understanding and the maximum number of points is 50, points can be assigned as follows:

  • Level 1—10 points (Fair understanding)
  • Level 2—20 points (Good understanding)
  • Level 3—30 points (Excellent understanding)

Using the same example as above, a range of points are assigned as follows:

  • Level 1—1 to 10 points (Fair understanding)
  • Level 2—11 to 20 points (Good understanding)
  • Level 3—21 to 30 points (Excellent understanding)

Based on the above, assigning a range of points for each level allows the evaluator to determine how "excellent" an understanding is.

3.12 Point rated technical evaluation criteria - part C Potential findings
Type Description Rationale
Major non-conformance—policy (other) More than one score can be obtained based on the same information presented in the proposal submitted. In the above example, the evaluator could assign different points to different resources all of whom have the same level of experience. (Contravention of TB Contracting Policy sub-section 10.7.27)
Major non-conformance—policy (other) It is not possible to assign a specific score based on the scoring guidelines proposed. For each rated requirement, the scoring guide must clearly indicate how specific scores will be assigned. (Contravention of TB Contracting Policy sub-section 10.7.27)
Major non-conformance—policy (other) There is a discrepancy between the stated maximum points available for a criterion and the actual maximum number of points available. Refer rationale above.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.13 Point rated technical evaluation criteria—part D

If a minimum total number of points or a minimum number of points per rated criterion or both are required, it must be clearly stated.

Assessment guidance and notes

Various selection methodologies that are based on points assigned to point rated requirements, may also specify that for a bid to be considered it must achieve a minimum total number of points, minimum number of points per point rated criterion or both. In such cases, the bid solicitation document must state the minimum score required (either total or individual or both). Without this information, Suppliers will not be able to determine whether or not the resource they wish to offer will meet the minimum score(s) required. The potential selection methodologies that this could apply to include:

  • Best value defined as technically compliant response that has the lowest price per point, and
  • Best value defined as technically compliant response that achieves the highest combined rating of technical merit and price
  • Best value defined as technically compliant response that has the highest number of points

Information related to the minimum number of points or minimum percentage of the total points presented in various areas of the bid solicitation document must be consistent. Potential discrepancies include:

  • Minimum number of points or minimum percentage of the total points stated in one area of bid solicitation document contradicts the minimum requirement in another
  • Minimum percentage of points required stated in one area of bid solicitation document contradicts the minimum percentage of points calculated based on the minimum and maximum number of points specified elsewhere in the bid solicitation document
  • Clause portion of the bid solicitation document or scoring guide requires that bidders achieve a minimum total number of points or minimum percentage of total maximum points that is different than the sum of the minimum number of points required for all rated requirement

In the event that the Assessor notes that the original bid solicitation contains conflicting information regarding the minimum points required and the issue is corrected before the deadline set for proposals to be returned, a non-conformance shall not be raised. The Assessor shall note these facts in the comments field of the assessment report.

3.13 Point rated technical evaluation criteria - part D Potential findings
Type Description Rationale
Major non-conformance—policy (other) Bid solicitation document states that a minimum number of points is required (total or individual or both) but does not state what that minimum number is. Without stating the minimum number of points required, it is not possible to determine whether or not each bid solicitation response submitted should be deemed compliant or not. (Contravention of TB Contracting Policy sub-section 10.7.27)
Major non-conformance—policy (other) Discrepancies between information presented in the clause portion of the bid solicitation document related to minimum number of points or minimum percentage of the total points required and that specified elsewhere in the bid solicitation document. The contradictory information presented makes it impossible for Suppliers to present a compliant resource and could affect the selection process and consequently change the Supplier awarded the contract. (Contravention of TB Contracting Policy sub-section 10.7.27)
Minor non-conformance Clauses portion of the bid solicitation document states a minimum percentage of the total maximum points required. Neither the scoring guide nor the evaluation section of the bid solicitation document state the minimum number of points required. Failure to indicate the minimum total score required in terms of the actual number of points could cause confusion amongst bidders.

Finding does not meet the criteria applicable to a Major non-conformance.

Minor non-conformance Discrepancies related to total number of points or the minimum number of points for a point rated requirement. Discrepancy is an obvious error and would not affect the submission of bids or the evaluation conducted. Finding does not meet the criteria applicable to a Major non-conformance.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.14 Point rated technical evaluation criteria—part E

Point rated technical evaluation criteria must not unfairly restrict competition.

Assessment guidance and notes

Point rated technical evaluation criteria must not be construed as unduly restricting the ability of a Supplier to respond to the bid solicitation. Examples of such a situation includes, but is not limited to:

  • An unreasonable number of point rated requirements given the category, level, description of the work required in the SOW, etc.
  • Amount of experience required to gain the maximum number of points is unreasonable. Factors that can affect this conclusion include the category, level, description of the work required in the SOW, etc. For example, maximum points for a specific point rated criterion can only be achieved if the resource has a minimum of 25 years of experience
  • Points are assigned for certificate(s) where the need for the certificate is unreasonable given the category, level, description of the work required in the SOW (e.g. requirement is for category 2.15 Facilitator Consultant, level of expertise - junior. To get points, the certificate required Master Facilitator Certification)

    Note: Master Facilitator Certification is a higher certification level than Certified Professional Facilitator.

  • Points are assigned for specific experience that can only be obtained within a specific organization within a department or within a specific department. For example, points are assigned based on project management experience within a specific area or in a specific type of project within National Defence
  • Minimum number of projects required, the minimum duration of a project or both required to achieve the maximum score possible is unreasonable given the category, level, work described in the SOW, etc.

Note

  1. In some cases, specific experience using software or a system or other tool that is found only in the federal government may be acceptable. Example would be assigning points based on experience using the Financial Information System (FIS) in the federal government
  2. In some situations (e.g. IT Security Design Specialist), the skill sets required by a resource may be constantly evolving thus necessitating that the resource's experience be more recent than may otherwise be required
3.14 Point rated technical evaluation criteria - part E Potential findings
Type Description Rationale
Major non-conformance—policy (other) Point rated technical evaluation criteria fits one or more of the situations described in the Assessment Guidance and Notes section of this element and is considered to unfairly restrict the ability of a Supplier to respond to the bid solicitation. Evaluation criteria used must not be construed as providing a single Supplier with an unfair advantage or unduly restricting the ability of a Supplier to respond to the bid solicitation. (Contravention of TB Contracting Policy sub-section 9.1.1)
Observation (insufficient info) The point rated technical evaluation criteria appear to unduly restrict the ability of a Supplier to respond to the bid solicitation. The assessor does not have the necessary subject matter expertise or information to assign a non-conformance.
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the SOW is not on file. If the SOW was not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.03: Bid Solicitation—Content (Part A—Requirement Details, Competitive) or 3.04: Bid Solicitation—Content (Part A—Requirement Details, Non-Competitive)).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.15 Selection methodology—part A

The bid solicitation document must state how responses will be ranked and how the winning response will be selected.

Assessment guidance and notes

Bids submitted must comply with all requirements (e.g. supplier certifications, insurance requirements, financial stability, etc.) of the bid solicitation to be responsive. Selection methodologies available in the High Complexity Bid Solicitation and Resulting Contract Template (HC) include:

  • Responsive bid with lowest price that meets all mandatory technical evaluation criteria (refer SACC Clause A0031T)
  • Responsive bid that meets all mandatory technical evaluation criteria and has the highest combined rating of technical merit and price (refer SACC Clause A0027T)
  • Responsive bid with lowest price that meets all mandatory technical evaluation criteria and achieves the minimum total number of points, or minimum percentage of points or the minimum number of points for each point rated criterion (refer SACC Clause A0034T)
  • Responsive bid that meets all mandatory technical evaluation criteria and achieves the lowest price per point (refer SACC Clause A0035T)
  • Responsive bid that meets all mandatory technical evaluation criteria and achieves the highest number of points within the budget available for the requirement (refer SACC Clause A0036T)

Note 1: Selection methodology—Medium Complexity Bid Solicitation and Resulting Contract Template

The Medium Complexity Bid Solicitation and Resulting Contract Template (MC) does not appear to allow for a selection methodology based on combined rating of technical merit and price, but does allow all others. In addition, the MC template also allows for a selection methodology based on a bid solicitation that does not contain any technical evaluation criteria (refer SACC Clause A0069T). In such cases, the lowest cost responsive bid that complies with all bid requirements would be issued the contract.

Selection methodologies based on the highest combined rating of technical merit and price will assign a higher weighting of points to technical merit and a lower weighting to price. The higher the technical weighting, the more important the ability to perform the work is as opposed to cost. In this situation, the work or duties required, category, level, mandatory and point rated requirements all play a role in the Assessor determining whether or not the Contracting Authority was justified in using a higher combined rating.

In the event that the Assessor notes that the original bid solicitation is either missing information regarding the selection methodology or contains conflicting information regarding the selection methodology and the issue is corrected before the deadline set for responses to be returned, a non-conformance shall not be raised. The Assessor shall note these facts in the comments field of the assessment report.

Note 2: Temporary Help Services

Temporary Help Services (THS) selection methodologies based on competitive method 1 is lowest price responsive or right-fit and selection methodologies based on competitive method 2 is lowest price responsive or highest combined rating of technical merit and price or minimum point-rated or any other option except right-fit.

The rules for using the right-fit basis of selection are:

  1. To be declared responsive, a bid must:
    1. comply with all the requirements of the bid solicitation
    2. meet all mandatory criteria
    3. comply with the following pricing rules:
      • A band between -20% and +20% of the median hourly rate will be used when 3 or more bids are responsive to the mandatory technical criteria. Any bids outside of this band will be considered non-responsive
      • When only 2 bids are responsive to the mandatory technical criteria, the higher priced bid may be selected if the hourly rate is within 25% of the lowest priced
  2. Bids not meeting (a), (b), or (c) will be declared non-responsive
  3. The selection will be based on the following justifications only:
    1. Specialized education which will improve the quality of services to be provided
    2. Additional certifications which will improve the quality of services to be provided
    3. Additional experience which will improve the quality of services to be provided
    4. Knowledge of relevant government policies or procedures which will improve the quality of services to be provided
    5. Better proficiency in one or both official languages which will improve the quality of the services to be provided
  4. If only 1 bid is responsive to the mandatory technical criteria, the identified user should determine that the bid represents fair market value to Canada before awarding a contract
  5. Unsuccessful bidders must be advised of the results including the justification and the median rate used

Note 3

The requirements stated in this element apply to competitive bid solicitations only.

3.15 Selection methodology - part A Potential findings
Type Description Rationale
Major non-conformance—policy (other) Clauses portion of the bid solicitation document specifies selection method to be used (e.g. lowest cost—only mandatory requirements) but evaluation section of bid solicitation document either explicitly states or implies, through an example, that another selection criteria will be used (e.g. lowest cost per point—mandatory and rated criteria). Even though this may be an "administrative" error, the bid solicitation document cannot contain conflicting information regarding how bid responses submitted will be evaluated. (Contravention of TB Contracting Policy sub-section 10.7.27)
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because the bid solicitation document did not indicate a selection methodology. If the bid solicitation document does not contain the required clause related to the selection methodology, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.03 Bid Solicitation—Content (Part A—Requirement Details, Competitive).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.16 Selection methodology—part B

The evaluation/selection methodology specified in the bid solicitation document must demonstrate that best value to Canada has been attained.

Assessment guidance and notes

TB Contracting Policy (Appendix A—Definitions) defines best value as - The combination of price, technical merit, and quality, as determined by the contracting authority before the bid solicitation and set out in the bid solicitation evaluation criteria, and which forms the basis of evaluation and negotiation between buyers and sellers to arrive at an acceptable basis for a purchase and sale.

Potential selection methodologies that could be used include:

  • Responsive bid with lowest price that meets all mandatory technical evaluation criteria (refer SACC Clause A0031T)
  • Responsive bid that meets all mandatory technical evaluation criteria and has the highest combined rating of technical merit and price (refer SACC Clause A0027T)
  • Responsive bid with lowest price that meets all mandatory technical evaluation criteria and achieves the minimum total number of points, or minimum percentage of points or the minimum number of points for each point rated criterion (refer SACC Clause A0034T)
  • Responsive bid that meets all mandatory technical evaluation criteria and achieves the lowest price per point (refer SACC Clause A0035T)
  • Responsive bid that meets all mandatory technical evaluation criteria and achieves the highest number of points within the budget available for the requirement (refer SACC Clause A0036T)
  • Right-fit only applicable to THS and only when using competitive method 1

Demonstrating that best value has been achieved using methodology b) (i.e. technically compliant response that achieves the highest combined rating of technical merit and price) can be challenging. Selection methodologies based on the highest combined rating of technical merit and price will assign a higher weighting of points to technical merit and a lower weighting to price. The higher the technical weighting, the more important the ability to perform the work is as opposed to cost and the higher the potential premium Canada would have to pay for the higher rated work. In this situation, the work or duties required, the classification, the level, the mandatory and point rated requirements all play a role in the Assessor determining whether or not the Contracting Authority was justified in using a higher combined rating. The fifth selection methodology (i.e. technically compliant response that achieves the highest number of points) is commonly used for scientific work or where the outcome is based on a solution.

Note

The requirements stated in this element apply to competitive bid solicitations only.

3.16 Selection methodology—part B Potential findings
Type Description Rationale
Major non-conformance—policy (other) Selection methodology does not clearly demonstrate the achievement of best value. Work described in the SOW, or the lack of stringency in either the mandatory requirements or the rated requirements or both do not support the use of the selection methodology specified. (Contravention of TB Contracting Policy sub-section 9.1.1.)
Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because the bid solicitation document did not indicate a selection methodology. If the bid solicitation document does not contain the required clause related to the selection methodology, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.03 Bid Solicitation—Content (Part A—Requirement Details, Competitive).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.17 Supplier's list

Documentation must be on contract file that confirms the appropriate Suppliers were sent the bid solicitation document and when it was sent.

Assessment guidance and notes

CPSS ePortal allows the Contracting Authority to save an electronic copy of the initial and final search results. Without a copy of the initial and final search results on file, the Assessor will not be able to confirm that the following harmonized business rules have been applied.

  • $0 - $40k --> One supplier selected from the initial search results
  • All MoS at the exception of THS - $0 - North American Free Trade Agreement (NAFTA) or Canada Korea Free Trade Agreement (CKFTA) (effective July 1st, 2020) --> Minimum of two (2) suppliers must be invited from the initial search results by selecting two suppliers, or by selecting one supplier from the initial search results and allowing the CPSS Client Module to randomly select the second supplier, or allowing the CPSS Client Module to select two random suppliers
  • All MoS at the exception of THS - Over NAFTA or CKFTA to $3,750,000.00 --> Minimum of fifteen (15) suppliers must be invited from the initial search results. The Contracting Authority (CA) should select at least ten (10) suppliers with the remaining five (5) suppliers selected randomly from the CPSS Client Module. If the CA selects less than the minimum ten (10) suppliers, the CPSS Client Module will randomly select a sufficient number of suppliers to meet the minimum fifteen supplier requirement. If the CA selects more than fifteen (15) suppliers, but not all Suppliers, the CPSS Client Module will still randomly select an additional five (5) suppliers
  • THS competitive method 1 and method 2:
    1. System randomly chooses five (5) suppliers that are certified as diverse suppliers, three (3) being low volume
    2. System randomly chooses another six (6) suppliers
    3. Identified user chooses 0 to four (4) additional suppliers
    4. See rules for joint ventures (JV)’s

Without a copy of the documentation sent, it is not possible for the Assessor to confirm who was sent the bid solicitation document and when. Contracting Authorities (CAs) are not allowed to bypass any Supplier that has been randomly selected by the CPSS Client module. Cases of poor past performance by a Supplier must be dealt outside the bid solicitation process.

Note

For requirements valued at over NAFTA or CKFTA to $3,75M, suppliers from the initial search results list that have not been invited to bid may request a copy of the bid solicitation. The Contracting Authority has the option of not sending the bid solicitation in response to requests from a supplier not originally invited to bid if the evaluation of additional bids would cause unacceptable delays to the contracting process.

3.17 Supplier's list Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) Copy of the required documentation required to confirm who was sent the bid solicitation document is not on file and the Contracting Authority is unable to provide it. Without a copy of the documentation it is not possible for the Assessor to confirm compliance with a number of subsequent elements. (Contravention of TB Contracting Policy sub-section 12.3.1.)
Major non-conformance—policy (other) One or more Suppliers not identified in the search were sent the bid solicitation document. The purpose of the search is to identify a list of Suppliers who have resource(s) that have specific skills and experience required to perform the work. Suppliers that were not returned as a result of a search, presumably, should not be able to provide resources that meet the requirements (Contravention of TB Contracting Policy sub-section 4.1.3.).
Major non-conformance—policy (other) One or more Suppliers identified in the final search results was not sent the bid solicitation. Bypassing one or more Suppliers would result in some Suppliers not being provided an equal opportunity to propose resource(s) that could meet the requirements of the bid solicitation document. (Contravention of TB Contracting Policy 4.1.3.)
Observation (other) Compliance to this requirement cannot be determined because it could not be determined who the response to request for clarification or question was sent to. This situation occurs when, for example, the email addresses of the suppliers invited to bid were placed in the bcc field of the email. In such cases, the printed copy of the email will not display the email addresses.

The Assessor does not have the necessary subject matter expertise or information to assign a Major or Minor non-conformance.

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of either the initial or final search results is not on file. If either the initial or final search results were not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 2.01: Search Results—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.18 Notice of proposed procurement

Copy of the notice of proposed procurement (NPP) (if applicable) must be on file.

Assessment guidance and notes

For Requirements valued over NAFTA or CKFTA, an NPP must be posted on the government electronic tendering service (GETS). For requirements above $400K for Temporary Help Services (THS) only, an NPP must be posted on GETS. The NPP alerts qualified suppliers who were not invited to request a copy of the bid solicitation.

3.18 Notice of proposed procurement (NPP) Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) Copy of the required documentation is not on file and the Contracting Authority is unable to provide it. Without a copy of the documentation it is not possible for the Assessor to confirm compliance with a number of subsequent elements. (Contravention of TB Contracting Policy sub-section 12.3.1.)

3.19 Notice of proposed procurement—content

NPPs must contain, as a minimum, specific information.

Assessment guidance and notes

The following items, common to all harmonized MoSs in the CPSS ePortal, must be included in all NPPs where applicable.

  • Bid Solicitation Number
  • Organization Name
  • Publication Date
  • Bid Closing Date
  • Proposed contract period
  • Number of Contracts
  • List of SA holders invited
  • Requirement Description
  • Estimated level of effort
  • Category (ies) required
  • Number of resources required for each category
  • Minimum corporate security required
  • Minimum resource security required (if applicable)

Sample NPPs for SBIPS, TBIPS and TSPS are available to federal government users. When determining compliance to this element, Assessors must determine whether or not all required information as identified above have been incorporated into the NPP.

Note

Bid solicitation date (i.e. NPP posting date) and closing date does not have to be in the body of the NPP. This information is part of the header information required by Buy and Sell to post an NPP.

3.19 Notice of proposed procurement (NPP) - content Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) NPP fails to include all required information. TB Contracting Policy requires that, wherever practical, an equal opportunity must be provided to all firms to compete to ensure that Canada meets its obligations under the various free trade agreements. Failure to provide all required information could give the Suppliers specifically invited an unfair advantage. (Contravention of TB Contracting Policy sub-section 4.1.3.)
Major non-conformance—policy (other) There are significant discrepancies between the NPP and the bid solicitation document. Refer rationale above.
Minor non-conformance There are minor discrepancies between the NPP and the bid solicitation document. While the discrepancies are minor in nature and likely would not have impacted on the contracting process, such discrepancies could cause concern regarding the fairness of the process.

Failure to comply with the requirement does not meet the criteria applicable to a Major non-conformance.

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Minor non-conformance There are minor elements missing from the NPP. The missing elements would not likely have impacted the decision of a supplier to request a solicitation.

Failure to comply with the requirement does not meet the criteria applicable to a Major non-conformance.

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the NPP is not on file. If the NPP is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.18: Notice of Proposed Procurement (NPP)).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

3.20 Bid solicitation amendments

Amendments to the bid solicitation document must be provided to all Suppliers invited to submit a response.

Assessment guidance and notes

Contracting Authority may, during the response period, need to amend the bid solicitation document. Reasons for amending the bid solicitation document include changing the response closing date, revisions to the SOW, revisions to the technical evaluation criteria (mandatory or point-rated criteria or both), etc. Amendments to the bid solicitation document must be provided to all Suppliers including any Suppliers who may have previously indicated that they were not going to bid and all qualified suppliers not on the final search results but who requested, as a result of the posting of an NPP, and were sent a copy of the bid solicitation document. Suppliers have the right to amend their decision to respond or not respond up to the point in time when the response period closes. It is possible that, based on the new or amended information provided, a Supplier may change its mind and elect to submit a response.

Amendments to the bid solicitation document may not change any element of the original bid solicitation document that would invalidate the search conducted. Such changes include revisions to the category (ies), level, supplier security requirement, region/metropolitan area, etc.

Note

  1. Since an amendment to a solicitation will not likely result in an amendment to the NPP, the Contracting Authority must retain on file a copy of documentation that confirms that all suppliers initially invited and any suppliers that were part of the initial search results, who requested a copy of the bid solicitation were sent all amendments to the solicitation
  2. In some cases, the Contracting Authority may receive a request from a supplier that results in a change to the bid solicitation (e.g. extension to the closing date, change to the evaluation criteria, etc.). The Contracting Authority may respond to all suppliers via email as opposed to issuing a formal bid solicitation amendment. This email shall be treated as an amendment to the bid solicitation
  3. If suppliers are sent the bid solicitation amendment(s), and there is no documentation on file (refer element 3.17) that confirms that suppliers were sent the original bid solicitation document, the Assessor will assume that these suppliers were also sent the original bid solicitation. In such situations, the appropriate Major non-conformance will be raised in 3.17 and the appropriate Observation raised in this element
3.20 Bid solicitation amendments Potential findings
Type Description Rationale
Major non-conformance—policy (documentation) Copy of the amendment to the bid solicitation document is not on file and the Contracting Authority is unable to provide it. Without a copy of the amendment to the bid solicitation document it is not possible for the Assessor to confirm compliance with a number of subsequent elements. (Contravention of TB Contracting Policy sub-section 12.3.1.)
Major non-conformance—policy (documentation) Copy of the bid solicitation amendment is on file but the documentation (i.e. email) required to confirm who was sent the bid solicitation amendment(s) is not on file and the Contracting Authority is unable to provide it. Refer rational above.
Major non-conformance—policy (other) Amendment to the bid solicitation document was not provided to all Suppliers. TB Contracting Policy requires that all potential Suppliers be provided the same information. (Contravention of TB Contracting Policy sub-section 10.7.2 (b))
Major non-conformance—policy (other) One or more Suppliers not identified in the search or that did not request the bid solicitation were sent the amendment to the bid solicitation document. The purpose of the search is to identify a list of Suppliers who have resource(s) that have specific skills and experience required to perform the work. Suppliers that are not part of the initial search results, presumably, should not be able to provide resources that meet the requirements (Contravention of TB Contracting Policy sub-section 4.1.3.).
Major non-conformance—procedural Amendment to the bid solicitation document revised the category (ies), level, supplier security requirement or region/metropolitan area. Amending the requirements (category (ies), level, supplier security requirement, region/metropolitan area, etc.) used to conduct the search either invalidates the search conducted or gives the appearance of an attempt to manipulate the procurement process.
Observation (other) Copy of the bid solicitation amendment and covering email is on file. However, compliance to this requirement cannot be determined because it could not be determined who the bid solicitation amendment was sent to. This situation occurs when, for example, the email addresses of the suppliers invited to bid were placed in the bcc field of the email. In such cases, the printed copy of the email will not display the email addresses.

The Assessor does not have the necessary subject matter expertise or information to assign a Major or Minor non-conformance.

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of the bid solicitation document is not on file. If the bid solicitation document is not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 3.01: Bid Solicitation—Documentation).

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Observation (documentation) Compliance to this requirement cannot be determined because a copy of either the initial or final search results is not on file. If either the initial or final search results were not on file, then a Major non-conformance would already have been raised against a previous element (i.e. element 2.01: Search Results—Documentation").

Note: Recurrence of this finding may result in the issuance of a Major non-conformance.

Document navigation for "3. Bid solicitation preparation—Assessor Guidance Document—Supply Arrangement Requirements"

Date modified: